Front #252

ABTH 10.3

A train within CTC may be authorized to occupy a track or tracks within specified limits for a certain time period. Authority must include track designation, track limits, and either a time limit or the words "until released." What is this called?


  1. Track bulletin
  2. Track and Time
  3. Track permit
  4. Track warrant
Back #252
Flag

ABTH 10.3


Answer: Track and Time
Feedback:
A few reasons a train may receive Track and Time would be: - The train needs to be within the limits with another train or men and equipment. - The train simply needs to move bi-directionally to complete work event(s).